Monday, October 14, 2019

Actuator power relay switch


Actuator power relay switch installed.

   I ordered and received a two-relay card. I use a four-channel version to reverse the actuator power for forward and reverse movement.
   The two-channel unit controls the actuator power supply battery connection. This unit is controlled from the same script that moves the actuator, hence the solar array.
   When the script runs, now, the two-channel unit turns on and connects the battery bank to the boost converter. The boost converter boosts the battery voltage to that needed to drive the actuator, approximately 32vdc-36vdc.
   Previously, the unit was connected by manual operation of a mechanical switch.

Wednesday, August 14, 2019

Re-thinking the system



   The system is running well. There are some changes that are needed but are difficult to implement.
   Roof-top installations are the most popular now, but also the most inefficient. I opted for a single axis, sun tracking, ground mounted system. The most efficient is the two-axis tracking system. The hardware needed is being made, just not for consumers (complaint).
   Due to the lack of adequate hardware support by the industry, I've had to innovate my own single axis tracker. There are limitations in the range of movement in the panels. This can be increased by raising the system off the ground and/or adding a linear actuator with a longer reach.

   My current system uses one inch galvanized steel pipe as a mounting axis. Two rows of three panels each are mounted, one above the other. The pipe comes in ten foot lengths. The pipe is tilted at an optimum forty-five degrees, for this latitude. This creates a classic Pythagorean Isosceles  triangle.
The pipe forms the hypotenuse of the triangle. If I extend the length of the pie by adding a short segment to the bottom, one of the angles will change. To maintain the proportions, I will also have to raise the upper end of the pipe, and possibly add a similar short segment to the top end.

   I added a vertical ten foot section of strut to the left side to stabilise the upper and lower rows of panels. I need to add another to the left side.

   In thinking this over, I realize I could extend those struts and add at least one more row of panels to the top.

Of course, adding all this extra weight means I may need to replace the one inch pipe with a two inch pipe.

   I also consider adding a two foot extension to the bottom of the pipe.

   After all this, I'm reconsidering the use of concrete placed rectangular steel tubing along with fixtures to make a dual-axis tracker. The model for this is a unit on YouTube from a Chinese company. I have to consider whether the model is scalable, i.e. whether a larger model will hold more panels safely and scurely. Needless to say, cost is still a factor.


Monday, July 29, 2019

It's that time again.

Every so often, the Raspberry Pi orgnization issues a new release of the operating system for the Raspberry Pi. Most recently, and coincident with the debut of the Rapspberry Pi 4B+, is the Debian Buster operating system. Before Buster were Jessie and Stretch.

When a major update to the operating system is issued, I have to re-format the SD memory card.
Then install the memory image on the card. I have to add a couple of files in order to communicate with the RPi without using an external monitor and keyboard. I can go 'headless' and use my local wifi router and my laptop to run SSH sessions.

Once communications is established, I set some system parameters. Next, I begin downloading and installing programs and other software to run on the RPi.

This process, with testing, can take half a day or more. For this reason, I keep a backup of the SD card once I'm done with updates and modifications. This way, if a card goes bad or some damage occurs, I'll have a spare ready for installation. Just plug and run.

February 2025 update

 Over a year ago, a lightning strike destroyed or damaged most of my solar power station. Only the panels were spared. (except for one). The...